Call +61 (0)411 145 553


Safescape Ladder
Laddertube is fully enclosed, preventing salt water and rocks from entering the escapeway.
Safe Escapeway Ladder Installation
Laddertube is a cost effective alternative to galvanised steel ladderways.
Safescape can install Laddertube for you or contact us to discuss training options.
mining ladderway
Laddertube is quickly being embraced by mine sites across Australia.
Underground mining ladder
The design of Laddertube ensures it is safe and practical for the user to climb.
 
Pause
  Search

Safescape Blog

Mines are the ideal place for innovation. Whether it be underground or in the treatment plant every mine is different. These differences breed innovation as we apply new ideas to solve our unique problems. Because this is part of our every day lives, at Safescape we believe that miners don't get enough credit for their innovative ways. Our Great Mines Think Alike blog page has been created to give a forum for spreading the innovative systems that we see at different mines in our travels. If you are interested in having news of your innovation included in our blog, please contact us.

Mincor Installs First Plastic Escape Ladder in Western Australia

Publised on October 28, 2010 09:41 by Safescape

In late August, the Mincor team took the decision to bring forward Nickel production from the Miitel Mine in order to smooth out the yearly production profile.

In order to do this they had to re-design their escapeway system to account for two shorter than originally planned rises and organize for them to be mined and fitted out with new ladders.  The team at Mincor put the word out for quotes on ladderways and raisebore rigs with availability being the key criteria.

ARD were able to make a rig available at short notice with a 1.5m reamer.  The hole was bigger than required for the installation of Safescape Laddertube ladderways however the key criteria was still timeframe.  The project called for one 54m ladder and one 56m ladder to be installed at opposite ends of the Miitel mine.

ARD mobilized their rig and crew and started drilling in September.  Safescape arrived on site at the end of September and the first escapeway was commissioned in the first few days of October.  We came back to install the second ladderway after the second rise was complete and both ladderways were in place by the third week of October. 

The whole process from the decision, through design, mining and installation took 5 weeks for the first rise and 7 weeks in total for both.  An impressive feat considering it takes some businesses 6 weeks or more to process a capital requisition.

Rodney Goldsworthy, the OH & S Manager, Mincor Southern Operations, can be contacted on (08) 9020 8200 for feedback on the installation at Miitel.  